Skip to content
← All projects

Twin Heater power cabinet

We built a stainless steel power cabinet, checked the connections and handed over the measurement documentation.

Related service: Electrical panel building ↗

Work type
Cabinet assembly
Industry
Industrial installations
Period
04.2026
01power cabinet
INOXenclosure material
QCmeasurements and connection checks

Project goal

We built one power cabinet for the Twin Heater system, with measurement documentation and a check of every connection.

Project timeline

The stages in the order the scope was delivered.

  1. 01 / Stage

    Quote and materials

    We quoted the assembly and checked the materials needed.

  2. 02 / Stage

    Components

    We checked stock levels and the component orders on the client’s side.

  3. 03 / Stage

    Assembly

    We built the cabinet in a stainless steel enclosure, which calls for more precise machining.

  4. 04 / Stage

    Measurements

    We carried out measurements, checked the connections and handed over the measurement documentation.

Challenge

The stainless steel enclosure needed more precise and more time-consuming machining. We planned the work to keep that precision without moving the deadline.

Result

We handed over the cabinet and its measurement documentation on the agreed date. The photos show the actual workmanship of the devices, labelling and surge protection.

Tools and scope

  • Cabinet assembly
  • Stainless steel machining
  • Measurements
  • Connection checks