Assembly of five power distribution cabinets
We checked the documentation, prepared the layouts and built five power distribution cabinets, including measurements and a check of every connection.
- Client
- Exyte
- Work type
- Cabinet assembly
- Industry
- Industrial installations
- Period
- 05–08.2025

Project goal
The task was to build five power distribution cabinets to the supplied technical documentation and get them ready for successive shipments on the client’s schedule.
Project timeline
The stages in the order the scope was delivered.
- 01 / Stage
Documentation review
We reviewed the electrical documentation supplied for the five cabinets before starting work.
- 02 / Stage
Components
We checked stock levels and ordered the components needed for assembly.
- 03 / Stage
Cabinet layouts
We prepared layouts to match the design to assembly practice and catch errors before building.
- 04 / Stage
Assembly
We built the cabinets in shipping order, updating the schedule as delivery times changed.
- 05 / Stage
Testing and handover
We carried out measurements and checked every connection before handover.
Challenge
Shipping dates for the cabinets were tight, and component lead times and team availability kept changing during the work. We updated the schedule to keep assembly, testing and acceptance in the right order.
Result
We built all five cabinets, checked the connections and handed over the full set on the agreed dates. The photos show the actual workmanship, labelling and wire routing.
Tools and scope
- Electrical documentation
- Cabinet layouts
- Measurements
- Connection checks